Shed planning · Guide 5 of 5 · 5 min readUpdated
Read a shed material order and cost estimate
Turn wall and roof members into whole stock boards, distinguish surface allowances from cutting plans, and identify everything still missing from the price.
This guide covers a member tool. Sign-in and approval unlock the full planner and material results. Request free early access.
Price whole boards and surface materials
The materials budget includes the modelled wall and roof lumber, sheathing, cladding, roof covering, underlayment, soffits, fascia, listed roof trim and any selected insulation. Lumber from both assemblies is grouped by actual size, including individual header plies. Blanks are allocated to whole stock boards using shared offcuts, the entered saw kerf and spare-board percentage. Spares are rounded up by lumber size. The layout is a practical quantity estimate, not a guarantee of the cheapest purchase.
Select the board lengths your supplier carries. A member longer than every selected length stays a separate piece requiring a quote; it is not silently split into short boards, and automatic spares do not apply to those long pieces. Custom header depths and stock longer than 16 ft also need entered prices. Confirm availability, grade and any specified engineered product.
Enter each board or material unit price directly in its row. Starting rates are illustrative CAD budget inputs, not local quotes. Blank prices remain unknown; zero means no charge. A missing price changes the headline to Priced subtotal · incomplete and removes the cost-per-square-foot result until every included item is priced. Changing stock size, board length or roof sheathing thickness can introduce a new price row.
Connectors/fasteners and delivery are entered as total allowances, each included once. Both start at zero. The material subtotals exclude those two allowances. Surface quantities already carry the surface allowance; the budget does not add it a second time. On a single-slope roof, high-side flashing is priced separately and removed from the other-edge flashing quantity to avoid counting that edge twice.
The budget excludes concrete, floor joists and supports, foundation and anchorage, header fillers, extra backing, doors/windows, labour and tax. Concrete keeps its separate supply comparison. Material prices, stock lengths, kerf and spares are saved with the plan and included in printed estimates. Older plans receive the example pricing settings.
Match each quantity to its purchase unit
The sheet counts are 4×8 area equivalents, not a numbered sheet cutting layout. Material coverage, seams, laps, defects, orientation and available lengths can change the purchase.
| Result | What it includes |
|---|---|
| Wall lumber | Net member blank lengths and individual header plies. The materials budget separately allocates whole stock boards and spares. |
| Wall sheets | Gross exterior wall area plus the surface allowance, divided by 32 sq ft and rounded up. No credit for openings. |
| Cladding | Net exterior wall area after rough openings, plus the surface allowance. |
| Roof sheets and covering | Sloped roof area with separate eave and rake overhangs, plus the surface allowance. |
| Roof lumber | Individual rafters, ties, ridge board, blocking, ladder blocks and subfascia. Gross blanks include plumb-end allowance; no stock-length waste. |
| Soffits, fascia and roof trim | Selected surface or linear coverage with the surface allowance. Product laps, backing and ventilation details need checking. |
| Floor sheets | Timber-floor footprint with the surface allowance. No joist or support takeoff. |
Use the allowance intended for that material
Lumber spares are whole extra boards added after stock allocation and rounded by size. The sheet and finish quantities already include their surface allowance. Concrete and insulation each have independent allowance settings.
Do not apply one more blanket percentage to every displayed line without checking what is already included. Add known omissions, unsuitable pieces and job-specific contingencies explicitly. A surface-area sheet count still needs a practical cutting and delivery check.
Finish the estimate and keep a dated copy
Scan every row for an unknown price and every long member requiring a quote. Starting CAD rates are illustrative. Use matching product, grade, unit and length quotations, then review the total and its stated exclusions.
Concrete remains a separate supply estimate. Add foundation work, omitted floor framing, doors and windows, labour, tax and other exclusions once when building the overall job price. Connectors/fasteners and delivery are total allowances in the materials budget; check whether they cover the actual order.
Download project preserves the entered prices and settings. Print gives a field copy of the drawings, schedules and budget. Put the revision or quote date in your project name so a supplier can match the list to the same plan.

Request a quote